BOYNE ISLAND SMELTER TANK REMOVAL

BOYNE ISLAND SMELTER TANK REMOVAL

Industrial Demolition

BOYNE ISLAND SMELTER TANK REMOVAL

Snapshot

The Boyne Island alumina smelter, owned by Rio Tinto is located in the Gladstone region. DEMEX was engaged by Boyne Smelters Limited as a principal contractor to undertake removal of hazardous Spent Cell Lining material from five 5,000m³ tanks and  demolition of the tanks.

Project Role

Principal Contractor

Project Scope

Demolition was conducted over two stages using a controlled collapse method. The tanks were pierced with a long extendable pick arm attachment to release the material, followed by mechanical dismantling of the tanks. Due to the age of the tanks and impact of the Spent Cell Lining material, the structural integrity of the tanks was compromised, however, all tanks were safely demolished without any environmental or safety incidents.

Project Highlights

DEMEX received positive feedback from Rio Tinto for the efficient way in which the project was conducted and the team’s responsiveness which allowed the works to be  conducted at the ideal time and ahead of schedule.

Want to learn more? Talk to our Team

Subscribe and stay connected with news, insights and client project success

d

Everything your logistics business needs is already here! GlobeFarer, a theme made for transport service companies.

Support center 24/7

+ 3 759 315 - 6427

Get in touch with us

globe@qode.com