COFFS HARBOUR PRECAST YARD

COFFS HARBOUR PRECAST YARD

Urban & Commercial Development

COFFS HARBOUR PRECAST YARD

Snapshot

The works included the removal of all slab, inground services, inground moulds, above ground sheds and concrete structures, the latter of which encompassed the super-T moulds, concrete plinths, slabs, services, and driveways.

The expanse of the site and volume of works allowed for concurrent work zones, which meant that at one point during the project, 12 excavators were operating simultaneously.

Project Role

Sub Contractor

Project Scope

Works commenced with processing of the steel moulds, which involved hammering, oxy cutting and shearing, as well as processing to separate the concrete and moulds.

Once demolished, concrete was relocated to a stockpile for crushing with the western bay of the main shed demolished mechanically by two excavators fitted with shears and an extension pick custom designed by DEMEX.

Project Highlights

  • 99.72% of project waste recycled
  • 1,918 tonnes of scrap steel recycled
  • 1,084 tonnes of concrete recycled
  • Design and fabrication of the ripper attachment.
  • An innovative methodology using induced layover rather than induced collapse reduced the risk of flying debris falling outside the demolition work zone.
  • No major safety or environmental incidents.

Want to learn more? Talk to our Team

Subscribe and stay connected with news, insights and client project success

d

Everything your logistics business needs is already here! GlobeFarer, a theme made for transport service companies.

Support center 24/7

+ 3 759 315 - 6427

Get in touch with us

globe@qode.com