DEMEX was engaged as principal contractor by developer Carlingford Projects to undertake the structural demolition of the the 9 storey
highrise located at 43 Garfield Terrace.
DEMEX was engaged as principal contractor to undertake the structural demolition, which involved removal of significant amounts of asbestos containing materials (ACM) from the narrow site, which spanned just 40 metres of beachfront. DEMEX facilitated all early works on the project, including site compound preparation works, temporary works to Northcliffe Surf Club (adjacent to the building), removal of retaining walls, and coordination of services contractors.
Top down demolition on small 1,600m2 site in high density beachfront location.
Full scaffolding wrap and fully enclosed bubble of the building to provide wind protection, to facilitate asbestos roof grinding, and allow for safe removal of ACM.