SUMNERS ROAD BRIDGE

SUMNERS ROAD BRIDGE

Industrial Demolition

SUMNERS ROAD BRIDGE

Snapshot

DEMEX was engaged by BMD to carry out the demolition of the Sumners Road Bridge as part of the Sumners road interchange upgrade project.

Project Role

Subcontractor

Project Scope

The demolition of the existing bridge was completed over 2 weeks of night works as the Centenary Highway remained operational during the day. Full lane closures and traffic diversions had to be executed each night and the site had to be cleaned and opened for traffic flow during the day.

Each evening the DEMEX team had a 9 hour window in which to orchestrate traffic control, clear the site and existing concrete barriers, bring in the heavy machinery and ensure road protection measures were in place which included bog mats and steel plates. Once night work was completed, all traces of demolition, debris, machinery, and road protection needed to be cleared and the highway reopened for use.

The proximity of the bridge to neighbouring residential area required noise vibration and dust emissions to be closely monitored and kept to a minimum.

Project Highlights

The project was delivered safely, without incident, and within the proposed timeline.

Want to learn more? Talk to our Team

Subscribe and stay connected with news, insights and client project success

d

Everything your logistics business needs is already here! GlobeFarer, a theme made for transport service companies.

Support center 24/7

+ 3 759 315 - 6427

Get in touch with us

globe@qode.com