DEMEX was engaged by the Gold Coast City Council to carry out the demolition and removal of the Scotty Logan Lane Bridge which crosses Tallebudgera Creek in Tallebudgera Queensland.

Project Role

Subcontractor

Project Scope

The project required demolition and removal of the existing bridge, and removal of the concrete piers. Waterway usage needed to be restricted around the vicinity of the bridge during the demolition. 

After installing a silt curtain DEMEX engaged specialist saw cutters who worked off barges and used wire saws on a jig to separate the bridge spans from the piers. The detached bridge was then hoisted via a crane.

Project Highlights

The project was successfully completed over four days due to the carefully mapped out process, excellent project execution, and time management of all contractors involved.

Want to learn more? Talk to our Team

Subscribe and stay connected with news, insights and client project success

d

Everything your logistics business needs is already here! GlobeFarer, a theme made for transport service companies.

Support center 24/7

+ 3 759 315 - 6427

Get in touch with us

globe@qode.com