DALRYMPLE BAY STACKER RECLAIMER

DALRYMPLE BAY STACKER RECLAIMER

Demolition Consulting

DALRYMPLE BAY STACKER RECLAIMER

Snapshot

DEMEX was engaged by G&S Engineering, a subcontractor to BMA, to remove a large decommissioned coal stacker reclaimer which formed part of the Dalrymple Bay Coal Terminal’s infrastructure, which is used by multiple coal producing companies operating in the region.

Project Role

Subcontractor

Project Scope

The works were conducted in a live operating environment characterised by ship loading activities, overhead crane operations, and vehicle traffic. The client specified a requirement for the site to be left in pristine condition in order for it to be ready to receive new export material. 

Project Highlights

Completed in just 13 days with zero incidents, the crew processed the steel using one 48 tonne excavator fitted with a shear attachment, and for the thicker gauges of steel, oxy/LPG was used. In total over 450 tonnes of scrap steel was used and transported it to Raw Metal Corp in Mackay.

Want to learn more? Talk to our Team

Subscribe and stay connected with news, insights and client project success

d

Everything your logistics business needs is already here! GlobeFarer, a theme made for transport service companies.

Support center 24/7

+ 3 759 315 - 6427

Get in touch with us

globe@qode.com