DEMEX was engaged to complete the internal strip out the 1988-built Finlay Crisp Centre which consists of three multi storey buildings

Project Role

Subcontractor

Project Scope

The first stage of the strip out project commenced on the Allara House building in late 2020.

DEMEX had to construct a full height rubbish chute for the removal of debris from each level. Various slab penetrations were created to facilitate new lifts and stairwell forming part of the refurbishment design. Part of the project also included demolition of a suspended walkway three stories up between 2 of the buildings.

Project Highlights

One of the levels of Allara Hose was a high security are with the ceilings and walls constructed with reinforced steel and signal blocking materials

Want to learn more? Talk to our Team

Subscribe and stay connected with news, insights and client project success

d

Everything your logistics business needs is already here! GlobeFarer, a theme made for transport service companies.

Support center 24/7

+ 3 759 315 - 6427

Get in touch with us

globe@qode.com